Which two represent challenges that could be met by Data Center Virtualization? (Choose two.)

A. An organization is reporting that it takes 24 hours to provision new desktops.
B. An organization is reporting that servers become unavailable for a short time during unplanned downtime.
C. An organization's server team requires 1-2 hours of downtime for applications when performing planned hardware maintenance.
D. An organization's server team requires 5 business days to provision a new server.

Answer: AD


What are two available methods for updating VMware Tools on a virtual machine? (Choose two.)

A. Configure virtual machines to check for and install newer versions of VMware Tools.
B. Downloading the newest version of VmwareTools.exe from vmware.com.
C. Attaching VMware Tools ISO to the VM and manually updating.
D. Copy the updated files to C:\Documents and Settings\All Users\Application Data\VMware\ VMware Tools\.

Answer: BD